Intermin Resources begins work on a processing pathway for its vanadium resource

By Tharun George for Proactive Investors

Existing resource of 3.3B tonnes grading 0.4% vanadium and 295 g/t molybdenum.

Intermin Resources Limited’s (ASX:IRC) joint venture partner at the Richmond Vanadium Project in Queensland has commenced metallurgical sampling and compilation of an updated resource.

The aim of the metallurgical sampling is to develop a processing pathway to extract the metals (vanadium, molybdenum, nickel, copper) on a large commercial scale.

The new updated JORC 2012 resource is being compiled to take into account tenement boundary changes as part of the Queensland government’s tenement management policies.

Earlier this week, Intermin had executed the formal joint venture agreement with AXF Resources covering Intermin’s Richmond project.

AXF will sole fund and manage up to $6 million of technical beneficiation and commercialisation studies over four years to earn a 75% interest in the project.

Since 2008 Intermin has completed drilling, beneficiation test-work and directional studies at Richmond providing AXF with a substantial technical database from which to continue development.

AXF has now reviewed the outcome of Intermin’s earlier testwork and has designed follow up metallurgical and mineral dressing programs to be conducted on new bulk samples.

Suitable research institutes have been identified in China to conduct the testwork and bulk sample shipment is scheduled to commence in the December quarter.

Circa 1.2 tonnes of mineralised toolebuc limestone (Coquina) was collected from existing gravel pits within the project area in early August 2017.

The bulk samples will be sent to at least two research institutes in China to conduct trial tests of mineral and metallurgical processing for the extraction of vanadium and molybdenum.

The testwork and reporting is expected to take around 18 – 20 weeks after samples arrive.

With a globally significant resource of 3.3 billion tonnes grading 0.4% vanadium and 295 g/t molybdenum and increasing interest in the energy storage space driving prices up, the companies are aiming to rapidly unlock the value of this project.

The information contained in this article and provided by VanadiumCorp is sourced from third-party content in the public domain and is for general information purposes only, with no representation, guarantees of completeness, warranty of any kind, express or implied regarding the accuracy, adequacy, validity, availability, completeness, usefulness or timeliness of any information contained within. Please also excuse any syntax as authors and reposted articles are sourced from global origins. UNDER NO CIRCUMSTANCE SHALL WE HAVE LIABILITY TO YOU FOR ANY LOSS OR DAMAGE OF ANY KIND INCURRED AS A RESULT OF THE USE OF THIS REPOSTED ARTICLE. THE USE OF THIS ARTICLE AND YOUR RELIANCE ON ANY INFORMATION CONTAINED HEREIN IS SOLELY AT YOUR OWN RISK. VANADIUMCORP ALSO ASSUMES NO RESPONSIBILITY OR LIABILITY FOR ANY ERRORS OR OMISSIONS IN THE CONTENT OF THIS ARTICLE.